Both bids rejected for Paphos–Polis Chrysochous road project
Transport Minister Evi Tsolaki says the government remains committed to the road after both bids were rejected, with alternative approaches now under discussion.

Paphos, Cyprus. The tenders board rejected both offers for the Paphos–Polis Chrysochous road, Transport Minister Evi Tsolaki confirmed on Friday. She told the House finance committee that the board had reached its decision unanimously, an outcome she had anticipated.
Bids exceeded ministry estimate
Cyfield Construction’s offer was the lower of the two at €124.85 million, excluding VAT. Araco Construction and its joint-venture partner Geostroy submitted a bid of €128.94 million.
Against the ministry’s €90.2 million estimate, those offers were €34.65 million and €38.74 million higher respectively, a difference of approximately 40 per cent.
Tsolaki said one submission lacked essential documentation, while the other substantially surpassed the estimated cost. When the offers became public in April, the ministry had attributed the difference to wider rises in building costs and material prices over recent years.
First-phase design
The tender sought design and construction work for the highway’s first phase, covering approximately 15.5 kilometres between Ayia Marinouda and Stroumbi.
The plans envisaged an initial two-lane road, with scope to widen it to four lanes later. They also provided for five bridges, two tunnels, four overpasses and twelve underpasses.
Alternative approaches under review
Tsolaki reaffirmed the government’s intention to deliver the road. She said the project originated in the 1970s and had become increasingly difficult to implement as time passed, prompting an examination of alternative ways to proceed.
She also said she had convened a meeting on the next steps, with a four-lane road among the options discussed.
This news item was generated automatically by Cyprus Inform from publicly available materials. Report an error →